SoftBank admits $3.7bn of turbine deposits are worth nothing
It is the first time a large company has admitted in its own accounts that a piece of the AI build-out has been abandoned rather than delayed, and the company admitting it is one whose interest bill has doubled.
SoftBank, the Japanese group that has put almost $65bn into OpenAI, reported its first quarterly loss in almost two years on Tuesday (¥1.12tn, or $7.1bn, for the three months to September) when analysts had expected a profit (of ¥129bn). The cause was an admission that deposits it paid to secure power-generation equipment for its 8-gigawatt data-center project in Ohio and other American sites are now worth nothing ($3.7bn of non-refundable advance payments, per Bloomberg). Companies miss forecasts all the time. Swinging from an expected profit to a loss this size, on money handed over for machinery that has not even been delivered, is the first time a big player has written off part of the AI build-out itself rather than pushing it back.
The mechanism is worth being precise about. Nobody built anything and lost it. SoftBank paid deposits to jump the queue for turbines and generators, the same queue Anthropic paid $3.4bn to join last week through Caterpillar, and has now decided those deposits are not worth what it paid. Yoshimitsu Goto, its finance chief, said there is no plan to shrink the Ohio project but that a "thorough reassessment" of purchasing is under way. He did not say why the payments had lost their value: whether the equipment is no longer needed on the original timetable, whether the supplier contracts have gone bad, or whether the group simply ordered too much. That gap matters. A deposit lost to a delay is the cost of waiting. A deposit lost because the project has shrunk is the first write-off of the build-out itself.
For our meter this does not add to the pile of risk. It is a price that was tested and failed: something SoftBank's books said was worth $3.7bn turned out to be worth nothing, and now we know. No new debt was taken on. The second number is the one still moving. The group's interest bill for the six months to September more than doubled (to ¥676bn). Last week's reporting had SoftBank adding roughly $40bn of debt in a year to pay for, among other things, that OpenAI stake. Kazuki Sawamura of Shinkin put it plainly: the data-center loss can be treated as temporary; "the more worrying factor is the increase in financial costs." A company that borrows to pay deposits on hardware it then writes off is paying interest on nothing.